Basements - Installing the Support Beams
Step 1 - Place the metal I-beams from side-wall to sidewall. There will be approximately 1 beam per 10' (left and lower left).
Step 2 – Set the support poles down the middle to support the center weight of the home (lower right).
Step 3 – Have the house mover lower the home onto the basement walls (no picture).
Exterior Finish Work
Step 1 - Once the house is lowered down, wrap 6 mil sheathing around the basement walls and carefully backfill. Backfill half way up with pea rock and the remainder of the way with dirt. The dirt should be compacted as its filled (left).
Step 2 – Install the window wells. Ideally, a piece of drain pipe from the window well should be connected to the drain tile system before any backfilling is done. If not that, then the windows should have a cover (left). Finally, install siding on the part of the basement walls that are exposed above the ground (no picture).
Interior Finish Work
Step 1 – Add insulation and a vapor barrier to the exterior walls (left).
Step 2 - Cut an opening into the home and construct the stairs. The stairs will have to be located in the middle of one side of the home, presumably in an area that will involve the least amount of obstructions. Even then, most likely at least one steel beam will have to be cut and braced from below with posts.
Step 3 - Finish off the rest of the basement to your liking (left).
Building the Basement | Basement Options
|
Featured Product |

Required reading for anyone who lives in a mobile home!
The book covers many manufactured home repairs and upgrades. A must for the do-it-yourselfer. Now on sale! Need this manual
now? Then download it.
More Info | Order here |
 |